Efficiency Improvements: Kitchener-Wilmot Hydro has replaced exterior cladding of facility and upgraded insulation from R12 to R20.
Lighting Retrofit Continuation: They have replaced hundreds of fluorescent lighting with energy efficient LED lighting including in the cafeteria, truck bay, underground crane room, line shop and mechanic shop.
Occupancy Sensors: Installed occupancy sensors to detect occupancy of a space and regulate lights and HVAC system.
Roof Replacement: Rebuilt 27,000sqft plant roof with improved design that will increase the building’s thermal resistance and insulation.
Lighting Retrofit: Converted all lighting in the control room & boardroom to LED bulbs. This project is estimated to have annual energy savings of 11,400 kWh/year.
Bathroom Retrofit: Low flow toilets and faucet motion sensors were installed in all office bathrooms.